Infrastructure Condition In North Sumatera
Road
The length of Road in North Sumatera was 34,575.494 Km year 2010, State Road 2,098,080 Km, Provincial Road 2,752,410 Km and Regency/Municipality Road 29,725,004 Km.
Road Development Plan :
- Development of Medan – Binjai Toll Road (±16 Km) and Tanjung Morawa – Tebing Tinggi Junction Kuala Namu (±60 Km) Toll Road.
- Development of Lake Toba Outer Ring Road.
- Development of Beach Side Road.
- Development of Tanjung Morawa – Saribu Dolok – Tongging Road (±90 Km).
Railway Networks
The length of railway was 556,349 Km of which 480,699 Km was being operated with rail type configuration R – 25 (42.92%) R – 42 (35.52%) and R – 33 (21.56%).
Available Railway Networks :
- Belawan – Medan – Tebing Tinggi – Kisaran – Rantau Prapat
- Medan – Tebing Tinggi – Pematang Siantar
- Medan – Kisaran – Tanjung Balai
Railway Development Plan :
Development of Railway Networks as follows Medan – Aras Kabu – Kuala Namu
Improvement of Railway Networks :
- Aceh Boundary – Binjai – Medan – Tebing Tinggi – Kisaran – Rantau Prapat.
- Tebing Tinggi – Pematang Siantar dan Kisaran – Tanjung Balai.
- Reopening of Railway Network of Besitang - Langsa – Lhokseumawe – Banda Aceh ±485 Km (to support the Trans Sumatera Railway Project Plan).
Airports
|
Airport |
Size (m2) |
Appron (m2) |
| Polonia, Medan |
2,950 x 45 |
49.455 |
| Dr. F.L. Tobing, Cental Tapanuli Regency |
1,710 x 30 |
50 x 95 = 4.750 |
| Pinang Sori, Sibolga Municipality |
1,400 x 30 |
- |
| Binaka, Gunung Sitoli Municipality |
1,350 x 50 |
40 x 60 = 2.400 |
| Aek Godang, South Tapanuli Regency |
1,400 x 23 |
32.5 x 58.5 = 12.901 |
| Lahondre, Pulau-Pulau Batu |
850 x 23 |
25 x 50 = 1.250 |
| Sibisa, Parapat |
750 x 23 |
40 x 60 = 2.400 |
| Silangit, Siborong-borong |
900 x 23 |
40 x 60 = 2.400 |
Airport Development Plan :
- Development of Kuala Namu New Airport in Deli Serdang Regency.
- Improvement of Pioneering Airports in the Regencies/ Municipalities of North Sumatera, e.g. Aek Godang F.L. Tobing, Binaka, Silangit, Sibisa.
- Development of Pioneering Airports in the Regencies of Mandailing Natal, Labuhan Batu and Tanjung Balai.
Seaports
Cargo Traffic Based on Seaports (Ton) in Year 2010
|
Seaport |
International |
Inter-Island |
||
|
Unloading |
Loading |
Unloading |
Loading |
|
| Belawan |
2,192,030 |
4,505,600 |
6,680,043 |
474,127 |
| Sibolga |
- |
8,246 |
490,345 |
589,333 |
| Tanjung Balai |
231,045 |
188,265 |
1,751 |
1,747 |
| Pangkalan Susu |
- |
- |
- |
- |
| Gunung Sitoli |
- |
- |
631,338 |
201,741 |
| Kuala Tanjung |
552,222 |
1,461,498 |
219,581 |
90,472 |
|
Total |
2,975,297 |
6,163,609 |
8,023,058 |
1,357,420 |
Seaport Development Plan : Improvement of Belawan Seaport and other Seaports, e.g. Teluk Nibung, Bagan Asahan, Labuhan Angin, Sibolga and etc.
Regional Expansion
Currently available Industryal Regions are : Medan Industrial Region (Kawasan Industry Medan/KIM) I & II and Star Industrial Region in Tanjung Morawa.
Regional Expansion Plan :
- KEKI (Kawasan Ekonomi Khusus Investasi) - Special Investment Economic Region consisting of Medan – Deli Serdang, Serdang Bedagai, Asahan, Tanjung Balai, Sibolga and Central Tapanuli.
- National Strategic Regions : Medan, Binjai, Deli Serdang dan Karo (Mebidangro).
- Danau Toba Region.
- Bukit Barisan Highland Agropolitan Regions (9 Regencies/ Municipalities).
- Agromarinepolitan Regions (16 Regencies/Municipalities).
Power Plants
- Install capacity - 1,413.59 MW
- Average capacity at peak load - 980 MW
- Electricity demand - 1,070 MW
- Electricity Deficit - 100 – 150 MW
Additional Capacity Plan of Power Plants up to the year 2011 is 1,938.2 MW.
Gas
- Supply capacity - 36 mmscfd
- Demand - 54 mmscfd
- PLN (National Electricity Company) - 42 mmscfd
- PGN (National Gas Company) - 12 mmscfd
- Deficit - 18 mmscfd
- Additional Demand - 104 mmscfd
Gas Demand Fulfillment Plan :
Long-Term - Accelerate Gas Production of Tac Glagah Kambuna. Current status in in the preparation of selling gas.